Example project listBuild your own Project List →
Project List

Sample Superintendent

Civil Site Superintendent · Houston, TX
Projects
Brazos Bend 54-in Sanitary Trunk Sewer and 30-in Water Main Relocation
Lower Brazos Regional Utility Authority · Richmond, TX · Hargrove Underground Utilities Inc. · Site Superintendent
Jan 2024 – Oct 2025 · 22 months · Start-to-finish
Total project value: $64M
Value of the work you ran: $38M
  • 9,800 LF of 54-in gravity trunk sewer at 25–35 ft with 12 manholes and four live tie-ins under bypass pumping
  • 6,200 LF of 30-in ductile iron water main relocated along a live four-lane arterial; trench boxes, wellpoint dewatering, two 36-in casing bores
  • Ran 32 field staff and 3 foremen; finished three weeks early, no lost-time incidents
Cedar Hollow Ranch, Sections 1–4 (1,150-lot master-planned community)
Cedar Hollow Development Partners · Kyle, TX · Jameson Excavation Limited · Site Superintendent
Mar 2022 – Dec 2023 · 21 months · Start-to-finish
Total project value: $27M
  • 1.1M CY of mass grading, two regional detention ponds and 38,000 LF of water, sewer and storm for 1,150 lots
  • 6.2 lane-miles of subdivision paving with curb, gutter and sidewalk; four sections released to builders on a rolling schedule
  • Three crews, 40 field staff; every section delivered on the builder release dates, on budget
Page 1 of 2
Project List

Sample Superintendent

Civil Site Superintendent · Houston, TX
Prairie Gate Data Center Campus, site civil package
Hyperscale owner, via general contractor · Temple, TX · Caprock Civil Constructors LLC · General Superintendent
Jun 2020 – Nov 2021 · 18 months · Start-to-finish
Total project value: $310M
Value of the work you ran: $44M
  • Site civil for two 36 MW buildings: 850,000 CY of cut-and-fill, building pads to ±0.1 ft, 14,000 LF of duct bank and 9,000 LF of storm and sanitary
  • Fire loop, chilled-water yard piping and substation pad built around the owner's energization sequence; 24/7 pours on the pads
  • Oversaw 4 superintendents and 110 field staff across two shifts; zero recordables in 18 months
FM 1626 Widening and Onion Creek Bridge Replacement
TxDOT, Austin District · Hays County, TX · Lone Star Highway & Bridge LLC · Bridge Foreman
Aug 2017 – Apr 2020 · 32 months · Start-to-finish
Total project value: $52M
Value of the work you ran: $19M
  • Four-span, 480-ft prestressed concrete girder bridge: 36 drilled shafts to 60 ft, bents, caps and deck pours over a live creek
  • Phased traffic switches to keep two lanes open; MSE walls and approach embankments built in four stages
  • Led a crew of 14; all deck pours met TxDOT ride spec first time, no lost-time incidents
Page 2 of 2